Gandaki, November 3:
The upgradation work of the Pokhara-Mugling road under the Prithvi Highway has reached its final stage.
The project office stated that the physical progress of the western section (Pokhara-Jamune) of the road has reached 86 percent.
Engineer Bishnu Prasad Pandey of the eastern section stated that the construction company has completed the work on the eastern section (Jamune-Mugling) and handed over the road. “The Defect Liability Period (DLP) has begun following the completion of the road expansion and upgradation work,” he said, adding, “Even after the DLP, the responsibility for road maintenance will remain with the construction company for an additional five years.”
According to Engineer Pandey, out of the total 41.45-kilometer distance of this section, about two kilometers of road in Damauli and Dumre markets have been expanded and upgraded to six lanes, while the rest has been expanded to four lanes. He mentioned that 17 large and small concrete bridges have been constructed in the eastern section.
Engineer Pandey also noted that the ‘signature’ bridge over the Madi River in Tanahu is being constructed under a separate contract. The expansion and upgradation work of this road, which was originally built five decades ago, began in Baisakh 2078 BS.
The China Communications Construction Company had secured the contract to construct the eastern section for NPR 6 billion 21 million 31 thousand.
With the upgradation of this road, which serves as the lifeline of Gandaki Province, transportation services from destinations such as the federal capital Kathmandu and Chitwan to Pokhara have become smoother. Citizens are now able to travel on a wide four-lane road, leaving behind the suffering of dust and mud endured during the construction phase.
Krishna Bahadur Kunwar, Chief Engineer of the project’s western section (Pokhara-Jamune), stated that the target is to complete the work within the upcoming Mangsir.
“The work on the western section has also reached its final stage, with about five kilometers of service lanes remaining to be blacktopped,” he said. “Related works ranging from road marking, placing traffic signs, to road safety are being carried out rapidly.”
Engineer Kunwar stated that preparations are underway to blacktop service lanes from Amar Singh Chowk to the Seti Bridge in Pokhara Metropolitan City-10, as well as in the Talchowk and Budhibazar areas.
He noted that a one-year Defect Liability Period (DLP) will also apply to the western section after the completion of the construction work. “Although the road is handed over, according to the contract agreement, the construction company will handle the DLP for one year and maintenance for five years,” he said.
Engineer Kunwar stated that out of the total 38.88-kilometer distance of the western section, 18.5 kilometers have been built with six lanes, and the rest with four lanes. “Since the western section has more urban areas, the road has been expanded to six lanes,” he said, adding, “Six-lane roads have also been constructed in Dulegaunda and Khairenitar on the Tanahu side.”
Out of the 13 bridges in this section, 12 have already been constructed, while the signature bridge over the Seti River in Pokhara is being built under a separate contract.
The agreement for the western section, connecting Jamune in Tanahu to the tourist capital Pokhara, was signed on Jestha 2, 2078 BS, and work commenced on Bhadra 12, 2078 BS. The Chinese construction company Yanhui Kaiyuan Highway and Bridge Construction had won the contract for the western section for NPR 7 billion 40 million 46 thousand.
The expansion and upgradation of the total 81-kilometer Pokhara-Mugling road have been carried out with loan assistance from the Asian Development Bank (ADB). Following initial delays in the implementation of this high-priority government road project, tourism entrepreneurs in Pokhara and others had mounted pressure to prevent further slackness.
The upgradation of the main roadway connecting the capital of Gandaki Province has helped boost economic and tourist activities in the region. The ordeal faced by tourists and general publics of having to endure hours of travel through dust and mud while commuting to and from Pokhara has come to an end.
Alongside the road expansion, narrow chowks in Pokhara now look open and attractive. Structures violating standards have been removed from areas such as Amar Singh Chowk, Arghau Chowk, Buddha Chowk, and Talchowk, widening the roads and junctions.
— RSS