Baglang, November 11:
The construction of the Harichaur-Malm-Pandavkhani road in Baglung, which was contracted to be completed within two years, remains unfinished even after four years. The physical progress of the eight-kilometer-long road has only reached 80 percent so far.
According to the Road Division Office, Baglung, the road being constructed under the “One Electoral Constituency, One Strategic Road Program” has finally reached the stage of blacktopping after four years. Office Chief Hari Subedi stated that the contractor is currently carrying out base-laying work prior to blacktopping.
The road contract was signed in September 2022 for Rs 252.8 million and was scheduled to be completed and handed over by September 2024. However, as the work was not completed within the stipulated timeframe, the deadline has been extended twice. The second extended deadline is set to expire this coming December. Locals have expressed ongoing doubts as to whether the work will be completed within this timeframe.
Due to the failure to construct the road on time, local residents were forced to travel through dusty roads for a long time. Galkot Municipality-7 Ward Chairman Raj Bahadur Thapa mentioned that construction has recently gained momentum following persistent vigilance and public grievances from locals.
According to Sagar Bhandari, Information Officer and Engineer at the Road Division Office, the deadline was extended for a second time and continuous pressure was exerted on the contractor after the work was not completed on time. He noted that following this, the contractor returned to work and is currently engaged in base-laying and leveling the road.
The contract for the road construction was awarded to Worldwide/Lopurna JV. Frustrated by the delays, local residents had even staged a protest against the construction company last November.
— RSS