नेपाल विद्युत् प्राधिकरण
GANDAKI, Nov 12:
Under the Pokhara-Bharatpur Distribution System Strengthening Project of the Nepal Electricity Authority (NEA), physical progress has reached 82 percent in Pokhara and 95 percent in Bharatpur.
Project Chief and Engineer Ananda Subedi informed that the project, initiated by the Authority four years ago to underground electrical wires, aims to complete the work in Pokhara by coming Vaishakh and in Bharatpur by coming Mangsir. According to him, the work in Bharatpur has reached its final stage.
Out of the planned 223 kilometers of electrical wires to be undergrounded in Pokhara, wires have been laid across 165.7 kilometers so far. Engineer Subedi stated that electricity is already being supplied through the underground system across 55.2 kilometers of this area.
In the first phase, the Authority has prioritized working in Pokhara’s main urban areas and locations with high tourist movement. Underground electricity service is already operational for over 400 households along the Prithvi Highway area, stretching from Chauthe in Pokhara Metropolitan City-14 to Kundahar, Amar Singh Chowk, Buddha Chowk, and Seti Bridge.
He also shared that wire-laying work has been completed on the main road connecting Seti Bridge to Prithvi Chowk, Sabhagriha Chowk, Srijana Chowk, Zero Kilometer, and onward to Lakeside.
Wires have also been laid in the inner alleys of Lakeside, with only the power supply remaining to be activated. Currently, wire-laying work is underway in some sections of the road connecting Sabhagriha Chowk through New Road to Chipledhunga, and Srijana Chowk through Nagdhunga toward the Talbarahi Temple in Lakeside.
“Since the Seti Bridge is under construction, power cannot be immediately supplied through the wires laid toward Prithvi Chowk,” Engineer Subedi said. “As the bridge construction is in its final phase, electricity service through the underground system will soon be operational in the remaining areas as well.
Under the project, along with Pokhara’s main highways, wires are also being undergrounded on secondary roads. Alongside electrical cables, optical fibers for telephone, cable television, and internet services are also being laid.
The project office stated that old utility poles and wires have been removed in areas where the underground system has come into operation.The target is to provide underground electricity service to 6,000 households in Pokhara.
Similarly, out of the planned 156.33 kilometers of electrical wires to be undergrounded in Bharatpur, wires have already been laid across 155.37 kilometers. Engineer Subedi informed that electricity has been supplied across 137.87 kilometers of this network. The target is to deliver underground electricity service to 1,200 households in Bharatpur.
Replacing messy and dilapidated electricity poles with underground wiring is expected to preserve urban aesthetics and reduce the risk of accidents.
In January 2022, the Indian company Tata Projects was awarded the construction contract for the project.
The Authority has been operating the distribution system strengthening project in Pokhara and Bharatpur with concessional loan assistance of approximately Rs 3 billion from the Asian Development Bank.
— RSS