Kathmandu, October 7
With approximately a week remaining until the major festival of Dashain, travelers returning home from Kathmandu and other urban centers are advised to verify road conditions prior to embarking on their journeys, following widespread damage caused by persistent rainfall since late August.
Due to severe monsoon rains, floods, and landslides occurring since late September, key national highways and rural road networks have been severely impacted. Travelers heading home for Dashain are strongly advised to check road conditions before departure.
- Galchhi–Betrawati–Syabrubesi–Rasuwagadhi Road: Completely blocked at Syabrubesi and Timure due to overflowing rivers.
- Beni–Jomsom–Korala Road: Closed due to major landslides at Thasang, Sukebagar, and Kavrebhir.
- Hilsa–Simkot Road: Completely shut due to heavy snowfall and river flooding.
- Dumre–Besisahar–Chame Road: Blocked after floodwaters washed away three wooden bridges in Chame and 60 meters of road at Bagarchhap.
- Kanti Lokpath & Bhimphedi Routes: Night travel is strictly restricted; open only between 5:00 AM and 5:00 PM.
- Prithvi Highway (Nagdhunga–Muglin): Open for two-way traffic, but high landslide risks exist at Krishnabhir, Jhauwang Khola, and Fisling, leading to long traffic jams.
- BP Highway (Dhulikhel–Sindhuli–Bardibas): Open only for small vehicles via temporary diversions managed by the Nepal Army and Department of Roads. Heavy vehicles remain banned.
- Prithvi Highway (Narayangadh–Daunne Section): Operational, but ongoing road expansion work has caused dust, potholes, and delays.
The Department of Roads and the Ministry of Physical Infrastructure and Transport are working on a fast-track basis to install temporary Bailey bridges and diversions before Fulpati to ensure smooth holiday transit.
Maldhunga Bridge Scheduled to Reopen Before Dashain
Repair efforts are underway to restore the Maldhunga Bridge—connecting Baglung and Parbat districts—which was damaged on September 27 by floods in the Kaligandaki River. The Road Division Office in Pokhara is expediting round-the-clock repair work to operationalize the bridge prior to the main festival period, while temporary alternate routes have been arranged to access Baglung Bazaar.
Alternate routes currently being utilized for travel and tourism activities include the Maldhunga–Beni route to Baglung, as well as the Phalebas–Jaiminighat route in Parbat. Transportation between the two districts has been disrupted for the past ten days following damage to nearly 30 meters of the approach road of the 114-meter-long bridge.
This disruption has also severed primary connections along the Mid-Hill Highway leading to Baglung, Rukum, and Rolpa. Officials from the Road Division Office in Pokhara stated that continuous 24-hour maintenance work will allow traffic to resume within a few days.
Observing the damage at the site, Chandra Prasad Dhakal, former president of the Federation of Nepalese Chambers of Commerce and Industry (FNCCI), emphasized the necessity of reopening the bridge promptly for local tourism, trade, and supplies, while ensuring clear communication regarding alternate routes to travelers and tourists in the interim.
Hari Subedi, Chief of the Road Division Office, affirmed that repairs using geobag and geogrid technologies are progressing swiftly, ensuring smooth travel for passengers heading toward Baglung and West Rukum before Dashain.

Three Motorable Bridges Completed Along Mid-Hill Highway in Kaski
Three concrete motorable bridges have been completed along the Kaski section of the Pushpalal (Mid-Hill) Highway, mitigating long-standing traffic bottlenecks caused by narrow bridges on widened road sections.
According to Engineer Ujjwal Sharma, Information Officer for the Pushpalal Highway Project Office in Parbat, two bridges measuring 52 meters each were constructed across the Yamdi River in Pokhara, alongside a 124-meter bridge at Panibihad near Ghattekhola in Annapurna Rural Municipality.
The completion of these structures aligns the bridge capacity with the existing road width, reducing accident risks, saving travel time, and improving traffic flow toward Parbat, Baglung, Myagdi, Mustang, and East Rukum. The three bridges were constructed under a single contract valued at NPR 215.9 million.
Maintenance Accelerated on Beni–Jomsom–Korala Road Section
Initial maintenance work has been completed across most affected points along the Beni–Jomsom–Korala segment of the Kaligandaki Corridor, following severe damage caused by recent monsoon floods and landslides at 55 locations.
According to Tejaswi Sharma, Chief of the Beni–Jomsom–Korala Road Project, major vehicles can now operate on most segments, excluding specific damage sites at Kunauta and Pokharebagar. Full vehicular access is targeted for resumption by next Monday as heavy machinery and technical teams continue clearing debris and rebuilding embankment walls.
Restoring access along this corridor remains a high priority to facilitate seasonal trade through the Korala border, transport local produce such as Mustang apples and livestock for the festive season, and support incoming tourist traffic.
Ram Kumar Rai