BHADRAPUR (Jhapa), November 2:
The local administration has initiated efforts to resolve problems encountered in the construction of the Kakarbhitta-Laukahi road section, which is being upgraded as part of the Asian Highway along the East-West Highway.
Following disruptions caused by local demands, shortages of construction materials, and issues in relocating electricity poles, the District Administration Office, Jhapa, has shown readiness to find a solution.
To identify the problems seen in road construction and find a way out, Chief District Officer Shravan Kumar Pokharel conducted an on-site inspection of the road section under construction on Saturday, accompanied by project representatives.
According to Ujjal Prasai, Regional General Manager of the construction company Evrascon-Kalika JV, road construction has been affected by local demands and problems in the availability of construction materials.
He stated that work had to be halted in several places after public representatives, political parties, and local residents demanded changes to the initial design to make the road systematic and commuter-friendly.
“On one hand, the government urges us to finish the work on time, while on the other, there are various obstacles here. Construction materials are not available when required,” said Prasai.
“The soil necessary for filling to construct the overpass has not been made available. Even after paying the required revenue for 300,000 cubic meters of soil, the process has not been advanced by the local level, affecting the work.”
According to Project Engineer Ashray Mahat, work has been hindered by demands such as building an overpass in Kakarbhitta which was not in the original design, managing a bus stand in Dhulabari, clearing obstructions in the Charali overpass area, and constructing an overpass near the school zone.
Along with local demands, problems have surfaced regarding the relocation of electricity poles and the sourcing and supply of construction materials. Electricity poles located in urban areas for road expansion could not be relocated on time.
Similarly, the project office reported difficulties in sourcing and regularly supplying asphalt chips required for blacktopping and backfilling materials used for constructing Reinforced Earth (RE) walls.
To resolve these issues, representatives of the construction company and the project visited the District Administration Office last Tuesday and briefed Chief District Officer Pokharel.
To gain first-hand information about the problems, the administration inspected the road under construction along with project representatives.
During the inspection, Chief District Officer Pokharel stated that discussions were held with stakeholders at various stages to prevent material shortages and resolve local-level issues.
“Discussions have been held with stakeholders at various levels, from public representatives to local residents, to prevent any problems in the project and ensure there is no shortage of construction materials,” he said.
“We conducted the on-site inspection to identify the actual problems and create a conducive environment for their resolution.”
He informed that coordination is underway with the Member of Parliament elected from Jhapa and the concerned local levels. He added that coordination has also been established with the Nepal Electricity Authority, Koshi Provincial Office, Biratnagar, to manage the electricity poles that need to be removed during road construction.
The 95-kilometer road from Kakarbhitta in Jhapa to Laukahi in Sunsari is being upgraded with financial assistance from the Asian Development Bank (ADB).
Of this, the contract for constructing the 45-kilometer eastern section from Kakarbhitta to Sitapuri was awarded to Evrascon-Kalika JV. The contract agreement for this section was signed for NPR 10 billion 6 million 94 thousand 82 thousand 712.
The project, whose construction began on Magh 19, 2080 BS, is funded by the Asian Development Bank (84.9%) and the Government of Nepal (15.1%).
According to Project Engineer Mahat, with about three months remaining for the construction contract to expire, the eastern section has achieved 56 percent physical progress so far.
He shared that the target is to push the progress to 70 percent within the contract period and complete construction within the current fiscal year.
Chief District Officer Pokharel has urged the construction company and project representatives to accelerate road construction while ensuring safe movement, well-managed diversions, adequate traffic signs, and effective traffic management.
— RSS