Myagdi, October 9.
The 202-kilometer Beni–Jomsom–Korala road section connecting China and India, running from Maldhunga in Parbat through Myagdi to the Korala border point in Mustang, suffered extensive damage from floods and landslides between September 24 and 27 (Ashoj 8–11).
Repair efforts have reached their final phase after landslides struck 50 different locations, causing road subsidence and riverbank erosion from the Kaligandaki River across 10 sections. Access roads at Kunauta Bhir in Raghuganga Rural Municipality-2 and the road bridge at Pokharebagar in Annapurna Rural Municipality were restored, allowing emergency vehicles to cross on Thursday evening. Constructing access routes at Kunauta and Pokharebagar—where floodwaters swept away the road—had presented significant challenges.
Tejaswi Sharma, Chief of the Beni–Jomsom–Korala Road Project, stated that the road currently allows only one-way movement for essential vehicles transporting fuel, ambulances, equipment, and relief material. Further repair works remain to be completed.
“Although initial repairs are complete, tasks such as fully clearing landslides, backfilling subsided and eroded sections, leveling the surface, and building proper crossings remain,” Sharma noted. “Operating general traffic in the current state poses risks of congestion and accidents. Therefore, we have formulated an action plan to complete repairs by Sunday and fully resume traffic operations from Monday.”
The Kaligandaki River caused severe damage through erosion and landslides in Kerabari, Lamabagar, Tilkenichaur, Rahupare, Siruwari, Kunauta, Mahbhir, Bhirkate, Dhirchyang, Ratopani, Tatopani, Sukebagar, Khambhitta, and Khaharekhola.
Narendra Subedi, Chief of the Federal Road Supervision Office in Pokhara, reported that out of the 33-kilometer segment in Myagdi where blacktopping was recently completed and concrete work was underway in landslide-prone areas, over 20 kilometers suffered heavy damage.
“Because this route connects to Korala, the only currently operational border crossing with China, the government prioritized restoring traffic within two weeks of the blockage. However, restoring it to its original condition will require significant investment and infrastructure,” Subedi said. “Damage to this road is estimated at NPR 900 million, and rebuilding it under a new design will require an additional budget of NPR 3 billion.”
Subedi, who is also the founding chief of the Beni–Jomsom–Korala Road Project, noted that this year’s flooding caused the most severe damage since the project’s inception. Excessive rainfall, collapsed feeder roads, debris (mucking) dumped along riverbanks by hydropower projects, fragile topography, new landslides, and rising water levels in tributary rivers collectively increased the volume of the Kaligandaki River, leading to unprecedented destruction.
Ganesh Gaire, Chief District Officer of Myagdi, stated that necessary preparations have been made to manage traffic challenges arising from freight vehicles traveling to and from Korala, exports of apples and potatoes from Mustang, tourist transport, and increased local travel during major festivals such as Dashain and Tihar.
Following customs clearance, over 500 cargo containers carrying goods imported via the Korala border for the Dashain festival remain stranded across various locations in Mustang and Myagdi, awaiting permission to proceed to their destinations.
“A team including public representatives and provincial security officials conducted an on-site inspection on Thursday to establish traffic management priorities for emergency services, essential freight, local transport, and tourist vehicles,” CDO Gaire stated. “Discussions were also held on deploying security personnel to narrow and hazardous points to prevent traffic jams.”
Because priority must be given to emergency services, local public transport, cargo containers, and trucks transporting apples and potatoes to markets, CDO Gaire requested visitors and tourists to postpone their travel plans for a few days until road conditions normalize.
A joint monitoring team inspected the road to review traffic resumption preparations, including Provincial Assembly Member Resham Jugjali, Acting Chief of the District Coordination Committee Dil Kumari Khatri, CDO Gaire, Federal Road Supervision Office Chief Subedi, Major General Bhola Nath Thapa of the Nepali Army’s Western Division, DIG Deependra Gharti Chhetri of the Gandaki Province Police, Armed Police Force (No. 4 Muktinath Brigade) Chief Deependra Shah, and Deputy Superintendent of Police Rajan Karki of Myagdi.
CDO Gaire added that, based on recommendations from stakeholders, a joint meeting of the District Security Committees of Myagdi and Mustang will convene on Friday morning to formulate a detailed action plan for regulating traffic along the Beni–Jomsom–Korala road section.