बेनी–दरवाङ सडक
Myagdi, October 7.
Flooding in the Myagdi River has eroded the Beni–Darbang road section at Balaute in Malika Rural Municipality-6, placing the nearby Dukhubesi settlement at severe risk. The flood, triggered by continuous rainfall from September 24 to 27, damaged the road—considered the vital lifeline connecting Malika, Mangala, and Dhaulagiri rural municipalities to the district headquarters of Beni Bazar—and heightened the hazard for local residents.
According to Beg Prasad Garbuja, Chairperson of Malika Rural Municipality, the erosion caused the road at the base of Dukhubesi to collapse, bringing a landslide dangerously close to the settlement.
“The flood in Arman Khola diverted the flow of the Myagdi River, causing intense bank erosion that washed away the road and disrupted vehicular movement along the Beni–Darbang route,” Chairperson Garbuja stated. “Although we have temporarily opened an alternative track connecting Dukhubesi to Tolabang by placing hume pipes across Dukhukhola, permanent road repairs and settlement protection remain indispensable for a long-term solution.”
The temporary alternative road is narrow, unpaved, and poorly graded, lacking sufficient space for heavy vehicles to pass each other. Vehicles frequently scrape their undercarriages, and there remains a constant risk of the hume pipes being swept away by sudden high flows. This route experiences heavy traffic, as it is also utilized by residents of Taman Khola in Baglung, as well as heavy vehicles transporting equipment and construction materials for six hydroelectric projects currently underway in the Myagdi Khola basin.
Rajesh Ulak, Senior Divisional Engineer and Chief of the Infrastructure Development Office in Myagdi—which oversees the Beni–Darbang Road Upgrading Project under the Gandaki Provincial Government—reported that a 100-meter section of the blacktopped road has completely collapsed from the outer edge to the inner wall.
The damage renders pedestrian transit through the site extremely hazardous. Er. Ulak emphasized that reconstructing the road will require building a solid retaining wall starting from the riverbed, as there is no margin remaining on the outer edge, and cutting into the hillside would further endanger the settlement above. Path Bahadur Roka, Ward Chairperson of Malika Rural Municipality-6, noted that the landslide threatens the safety of approximately 140 households residing in Dukhubesi village.
Local residents of Dukhubesi have called for immediate, coordinated action to stop further erosion, restore smooth traffic flow, and protect their homes.
In response to the critical situation, a joint inspection team visited the Balaute site on Tuesday to advance reconstruction plans. The delegation included Resham Jugjali (Subin), Member of the Gandaki Provincial Assembly elected from Myagdi 1 (2); Nawaraj Sharma, Secretary at the Ministry of Physical Infrastructure Development and Transport Management of Gandaki Province; Beg Prasad Garbuja, Chairperson of Malika Rural Municipality; and Dr. Mahendra Baniya, Senior Divisional Engineer at the Ministry.
Assembly Member Jugjali proposed executing traffic restoration, road reconstruction, erosion control, and settlement protection simultaneously. He emphasized reconstructing the road without causing immediate disturbance to the settlement to resume vehicular movement before the Dashain festival, while completing permanent river control structures before the next monsoon.
Ministry Secretary Nawaraj Sharma stated that a mutual understanding has been reached among key stakeholders: the Infrastructure Development Office will utilize available road maintenance budgets to purchase gabion wire mesh and pay labor wages while seeking additional funding; the Ministry will manage necessary financial resources; the Rural Municipality will supply riverbed construction materials; and local hydroelectric projects will mobilize heavy equipment to expedite execution.
Secretary Sharma added that the Ministry will ensure sufficient funding to promptly repair and reopen other disaster-damaged provincial road projects across Gandaki Province, noting that restoration work is already underway in several districts.