तटबन्धमा क्षति
According to Engineer Sagar Paudel, Information Officer for the Irrigation and Water Resources Project in Bharatpur, the flood damaged embankments on the Chitwan side across several areas: 600 meters in the Siddhiganesh forest area, 300 meters in the Majhuwa forest area, 100 meters in the Hirapur area, and 50 meters each in the Gaureswar, Gaujipur, and Katero areas. The floodwaters damaged the embankments and caused local inundation.
Er. Paudel noted that extensive embankment construction west of the Narayani Bridge on the Chitwan side prevented major disaster during the recent rainfall. Although floodwaters entered settlements through a few unembanked gaps, severe damage was averted. Conversely, he stated that the flood caused substantial destruction on the Nawalparasi side, where embankment construction remains incomplete.
In Nawalparasi, the flood damaged 3 kilometers in the Amaltari area and 2 kilometers across the Nandapur, Sitapur, and Seri regions. Furthermore, damage was reported across 15 kilometers in various locations stretching from Parsauni to Tamaspur and Baguwan, 500 meters from Khotesimal to Brahmasthan, 700 meters across Pithauji, Nauneghat, and Ghosarghat, and 1.5 kilometers in the Susta region. The severity of the damage in these areas is primarily attributed to the lack of protective embankments, whereas embanked sections suffered only minor damage.
Er. Paudel added that embankments cover only 9 kilometers of the 98-kilometer stretch downstream from the Narayani Bridge on the Nawalparasi side. Consequently, unembanked areas experienced severe erosion. Overall, while embankments effectively mitigated damage in Chitwan, the lack of infrastructure on the Nawalparasi side resulted in significantly higher losses.